How a Site Refit Quietly Raises Your KVA Costs

A refit is planned around the equipment, the budget and the programme. Electricity capacity rarely makes it onto the list. A business installs EV charge points, replaces gas heating with heat pumps, adds a new production line or upgrades its air conditioning, and the electrical installer designs the system to operate the equipment safely. But whether the site’s agreed electricity capacity can accommodate the additional demand, and what the implications could be for network charges, are questions that can be overlooked until the bills arrive.

That is how refits can quietly raise costs. New equipment may increase demand during the site’s busiest periods. If demand exceeds the capacity agreed with the network operator, additional charges may apply where the site’s tariff includes an excess capacity charge. In other cases, the existing electrical connection may not be sufficient to support the new equipment, making a capacity upgrade necessary.

That can introduce additional work, costs and delays that were not included in the original project budget.

The refit may have delivered exactly what the business wanted. The electricity capacity implications simply were not considered early enough.

The Equipment That Changes the Picture Most

  • EV charge points. Several chargers operating at the same time, particularly around the start or end of the working day, can introduce a substantial

  • new peak to a site that previously had little or no vehicle-charging demand.
  • Heat pumps and electric heating. Moving heating demand from gas onto the electricity connection can significantly increase electrical demand, particularly du
  • ring colder periods when heating requirements are higher.
  • Electric kitchen and process equipment. Replacing gas-fired equipment with electric alternatives can increase the site’s electrical load, especially when the new equipment operates alongside existing machinery.
  • Air conditioning and refrigeration. New or larger systems can add to demand during hot weather, when other electrical loads may also be high.
  • New production lines and machinery. Large motors and compressors can increase electrical demand. Their starting characteristics and reactive power requirements may also need to be considered as part of the site’s electrical assessment.

The effect of each installation depends on its power requirements, operating schedule and how it interacts with the site’s existing loads. The important question is not simply how much equipment is being added, but how much of it will operate at the same time.

 

Where Projects Go Wrong

The common problem is that responsibility for the capacity question can be fragmented. The electrical contractor focuses on the equipment and installation requirements. The facilities manager approves the works and project budget. The finance team sees the electricity bills after the project is complete, often without knowing which changes have affected the site’s demand.

Meanwhile, the agreed capacity, sometimes set years earlier for a different building or operating arrangement, may remain unchanged.

  • Nobody checks the site’s agreed capacity before the equipment is ordered, so the project proceeds without a clear understanding of the available capacity.
  • Commissioning involves several substantial loads operating simultaneously, or high demand is sustained during a relevant half-hour measurement per
  • iod. This can produce a recorded demand higher than the site normally experiences. A brief start-up surge alone will not necessarily translate into a high half-hourly demand reading.
  • A capacity increase is requested late, after the equipment has been installed, potentially delaying the point at which the business can operate it at the required level.
  • Load management is not considered. Staggering EV charging or equipment start times could help keep peak demand within the site’s existing capacity, depending on its actual demand profile.

These issues are not necessarily caused by poor electrical design. They often arise because the project’s scope does not explicitly include the commercial implications of the site’s agreed capacity and network charging arrangements.

 

The Cost Nobody Budgeted

Because these charges can appear as part of the electricity bill rather than arriving as a separate project invoice, they are easy to overlook. A project approved on the strength of its energy savings or sustainability benefits can end up with additional ongoing costs that reduce its financial benefits.

Where a site’s tariff includes excess capacity charges, exceeding the agreed limit can result in additional network charges. The exact charging arrangements depend on the site’s network operator and applicable tariff. The business may continue paying these charges before anyone connects the change in demand to the refit.

The opposite can also happen. Efficiency upgrades such as better lighting, high-efficiency motors and improved controls may lower a site’s peak demand, leaving its agreed capacity higher than its actual requirements. A refit can therefore create an opportunity to review capacity as well as a risk of increasing costs.

In both cases, the outcome depends on reviewing the site’s actual demand data rather than assuming that the existing capacity remains appropriate.

 

Why This Is Becoming More Common

Decarbonisation plans are steadily moving demand from gas, diesel and petrol onto electricity connections. Heat pumps replace gas boilers, electric vehicles replace petrol and diesel fleet vehicles, and electric equipment replaces gas-fired process machinery.

Each step can make sense on its own and may deliver genuine emissions savings. Collectively, however, these changes can place new demands on connections that were originally designed for much lower electrical loads.

A net zero plan that does not account for the site’s electricity capacity can underestimate the practical requirements and potential costs of electrification. This is particularly important for businesses rolling out upgrades across multiple locations, where each site may have different existing capacity and operating patterns.

 

What Happens When Capacity Runs Out

There are two separate issues to consider.

The first is whether the site’s electrical connection and internal installation can physically support the new equipment. If they cannot, the business may need an electrical assessment and a connection upgrade before the equipment can operate at the required level.

The second is whether the site’s demand exceeds its agreed capacity. The agreed capacity is commonly recorded as Maximum Import Capacity (MIC), although terminology can vary between network operators. Where the applicable tariff includes excess capacity charges, exceeding the agreed limit can result in additional charges.

If more capacity is genuinely required, the business may need to apply to its Distribution Network Operator (DNO) or work through an appropriate connection provider. The operator will assess the request and determine what work, if any, is required. Costs and timescales depend on the connection, the work involved and the applicable charging rules. Not every capacity increase requires wider network reinforcement, and the customer should establish which costs apply to the specific project.

This is not a problem if it is planned for. It becomes more difficult when the project is already complete, the equipment is installed and the business discovers that it cannot use it at full output until further work is completed.

Raising the capacity question during the design stage gives the business more time to assess its options, consider load management and arrange any necessary connection work.

Who This Hits Hardest

  • Businesses installing EV charging for fleets or staff without first assessing how simultaneous charging could affect site demand.
  • Sites moving from gas to electric heating as part of a decarbonisation plan.
  • Manufacturers adding production capacity or replacing old machinery with equipment that has different electrical requirements.
  • Multi-site businesses rolling out the same upgrade across several locations, each with different connection capacities and demand profiles.

Signs You Should Check Before or After a Refit

  • A refit is planned and nobody has compared the expected new load with the site’s agreed capacity.
  • Network charges have increased after recent works and nobody has investigated whether the change in demand is connected.
  • The project team has not assessed the capacity implications of the proposed equipment.
  • You are planning EV charging and solar together but have not assessed how the site’s import demand, generation and export arrangements will interact.
  • The business has added electrical equipment but has not reviewed its half-hourly demand data to understand the effect on peak demand.

The best time to deal with capacity is before the equipment is ordered. The next best time is as soon as an unexpected charge or capacity issue appears. Either way, the decision should be made using actual demand data rather than discovered on a bill.

Businesses that handle this well treat electricity capacity as part of the project scope from day one, alongside the equipment, installation and budget. They assess the expected new load against the existing connection, consider whether load management could help and identify whether a capacity change or connection upgrade may be necessary before committing to the works.

Check Your Capacity Before the Refit Costs You

A site upgrade should not create unexpected electricity capacity problems.

Ecotilities can help businesses review their agreed capacity and demand patterns through a kVA analysis, helping identify potential capacity issues and whether further investigation may be needed before or after a refit.

Visit ecotilities.co.uk/kva-analysis or call 0333 4422 050.

Questions Businesses Ask

Should we check our capacity before a refit or after?

Before is far better because it gives the project team time to account for existing capacity, load management or a possible connection upgrade. It also helps identify potential costs and delays before equipment is ordered. An assessment after the refit is still worthwhile, particularly if demand has increased or unexpected network charges have appeared.

Do EV chargers always push a site over its capacity?

Not always. It depends on the number and power rating of the chargers, how they are used and what else the site is drawing at the same time. Smart charging and load management can help control simultaneous demand. That is why the site’s existing demand profile and proposed charging requirements should be assessed together.

Can load management avoid the need for more capacity?

It can often help. Staggering vehicle charging or equipment start-up can reduce simultaneous demand and help keep the site’s peak within its existing capacity. Whether this removes the need for additional capacity depends on the site’s demand profile, operating requirements and how much flexibility is available.

How long does a capacity increase take?

It depends on the network operator, the size of the connection required and the work involved. Some relatively straightforward connections can be delivered within weeks, while larger or more complex projects may take months or longer. This is one reason to discuss capacity requirements with the network operator early in the project.

Could a refit reduce our capacity needs?

Yes. Efficiency upgrades such as improved lighting, more efficient motors and better controls may lower peak demand. If the site’s recorded demand has fallen, it may be worth reviewing whether its agreed capacity is still appropriate. Any reduction should be based on actual demand data and future requirements, because restoring capacity later may not always be straightforward.